When conducting Stage 2 DBPR compliance monitoring, are all sites required to be sampled on the same day?

It is not necessary to sample all sites on the same day. For example, a system on quarterly monitoring could sample in the third full week of every third month (Initial Distribution System Evaluation Guidance Manual, EPA815-B-06-002, January 2006).