If a system modifies its distribution system after completing its IDSE, is it required to complete a new IDSE?

No new IDSE report is required, but the system should work with its primacy agency to change its Stage 2 DBPR monitoring plan to address the changes to the distribution system.

For additional guidance on the Stage 2 Disinfectants and Disinfection Byproducts rule please visit http://water.epa.gov/lawsregs/rulesregs/sdwa/stage2/regulations.cfm.